The cost of the project is $201,257.10. Funding is available from the Ohio Public Works Commission in the amount of $148,930.25. The remaining $52,326.85 will be provided by the Lorain County Engineer through the County Engineer Motor Vehicle Gas Tax account.
The project was awarded to N & N Construction of Wakeman, Ohio.
The work will begin at 8:00 am on Monday, August 14th, 2023 and is expected to be completed by 5:00 pm on Friday, November 10, 2023 weather permitting.
Detour signs will be posted. Your cooperation during construction is greatly appreciated.
Please ensure your safety/service personnel are aware of this closure.